Every cutting or removal of a tree shall comply with, and every permit issued under this bylaw is subject to, the observance or fulfilment of the 8253581 Bylaw 8057 Page 14 following requirements, restrictions and regulations, to the satisfaction and approval of the Director :
- a) tree parts and woodwaste shall be properly disposed of by chipping or removal from site in accordance with all applicable City bylaws and Provincial regulations;
- b) each tree to be cut or removed shall be clearly identified with a flag, paint, survey tape or other such method;
- c) a tree protection barrier shall be placed around any tree or trees which are not to be cut or removed, in such a manner to ensure that the trunk, branches and root structure are not damaged by the cutting or removal operations. The tree protection barrier must be constructed prior to the issuance of the permit and must remain intact for any construction or demolition site throughout the entire period of construction or demolition;
- d) precautions shall be taken to ensure that trees which are not to be cut or removed are not be subject to any of the damaging activities prohibited by subsection 3.1.3;
- e) no tree cutting or removal activities may be carried out between the hours of 6:00 p.m. and 8:00 a.m. the following day;
- f) all damage to drainage facilities, watercourses, highways or other public or private property arising from the removal of a tree shall be promptly and properly repaired to the satisfaction of the Director at the expense of the permit holder;
- g) all watercourses, groundwater aquifers, waterworks, ditches, drains, sewers or other established drainage facilities shall be kept free of all woodwaste arising from or caused by the tree cutting or removal operations;
- h) all hazards or potential hazards arising from the tree cutting or removal operation shall be adequately fenced or otherwise protected for the safety of the public;
- i) tree cutting or removal operations must not encroach upon, undermine, damage or endanger any adjacent property or any setback area prescribed in the permit or a bylaw; and
- j) tree cutting or removal operations shall be limited only to the area specified in the permit which shall be clearly marked at the site and such markings maintained for the duration of the permit.
Short excerpt. The rest of the text is on the official source.
Official source · Table of contents
Topics
Related sections
- 4.8.1 If the tree cutting or removal operations authorized by a permit are not completed before the permit expires, or it becomes necessary to alter or deviate from the particulars of the permit application or the tree cutting and replacement plan submitted for a permit, the Director may renew, extend or modify the permit upon written request of the permit holder, subject to the following
- 5.1 Tree Cutting or Removal
- 5.1.2 The Director may issue a permit subject to the observance or fulfilment of any additional conditions specified in the permit which in the opinion of the Director are necessary to achieve the purposes of this bylaw
- 5.2 Protection of Retained Trees During Construction and Site Preparation
Other cities
To report a correction: info@bylawinsider.com. This link opens your mail program.
Unofficial copy for convenience; the official version governs. Official source
Short excerpts of a public bylaw PDF. The official PDF governs.