The CAO may delegate the authority under subsections (1) and (2) to the staff that oversees the noise exemption application process. 6B. (1) Subject to section 6, where a person makes an application for an exemption from the provisions of this By-law for construction noise and equipment:
- (a) for extended consecutive hours required to complete concrete finishing, concrete pouring, or any other associated activities as determined by the CAO;
- (b) due to a requirement to temporarily reduce noise impacts during the day as identified under an approved Construction Mitigation Plan under Administrative Order 2018-005-ADM; or
- (c) due to limited access of seven (7) days or less to specialized trades or specialized equipment; the CAO may grant an exemption.
Extrait court. Le reste du texte est sur la source officielle.
Source officielle · Table des matières
Pour signaler une correction : info@bylawinsider.com. Ce lien ouvre votre programme de courriel.
Copie non officielle, pour faciliter la lecture. La version officielle prévaut. Source officielle
Short excerpts of a public bylaw PDF. The official PDF governs.