Barrie By-law 2006-140, s. 7 — Vibration - Peak Particle Velocity Limit If the person in charge, of a blasting operation carries out routine monitoring of the vibration the peak particle velocity limit for vibration resulting from blasting operations in a mine or quarry is 1.25 cm/s
Noise By-law
Last checked
Indexed text
Vibration - Peak Particle Velocity Limit If the person in charge, of a blasting operation carries out routine monitoring of the vibration the peak particle velocity limit for vibration resulting from blasting operations in a mine or quarry is 1.25 cm/s.
By-law 2006-140 49 Office Consolidation The Corporation of the City of Barrie Noise By-law PUBLICATION NPC-205 SOUND LEVEL LIMITS FOR STATIONARY SOURCES IN 1 & 2 AREAS (URBAN) TABLE OF CONTENTS
Short excerpt. The rest of the text is on the official source.
Official source · Table of contents
Topics
Related sections
- 5 Concussion - Peak Pressure Level Limit If the person in charge of a blasting operation carries out routine monitoring of the peak pressure level, the peak pressure level limit for concussion resulting from blasting operations in a mine or quarry is 128 dB
- 6 Vibration - Cautionary Limit Subject to section 7 the peak particle velocity limit for vibration resulting from blasting operations in a mine or quarry is 1.00 cm/s
- 1 Scope
- 2 References
Other cities
To report a correction: info@bylawinsider.com. This link opens your mail program.
Unofficial copy for convenience; the official version governs. Official source
Short excerpts of a public bylaw PDF. The official PDF governs.